Phase 1: Define the Scope and the Schedule

  • Name one project lead with authority to make decisions.
  • Set the target move window and the latest acceptable restart date.
  • Identify which orders and deadlines fall inside the window.
  • Decide what is moving, what is being replaced and what is being sold or scrapped.
  • Confirm lease dates, landlord rules and any building approvals at both sites.

Phase 2: Inventory Every Machine and Asset

  • List machines with make, model, serial number, weight and dimensions.
  • Record the utilities each one needs: power, air, water, data, ventilation.
  • Note tooling, fixtures, spare parts and consumables that go with each machine.
  • Include benches, racking, shelving, carts and office equipment.
  • Tag every item with an asset number and a destination.

The inventory becomes your quote request, your move sequence and your checklist for the new site.

Plan the New Layout Before You Plan the Move

Mark every machine’s position on a scaled floor plan, including clearances and utility drops. It saves hours of repositioning on move day and tells you what the new space needs before the first machine arrives.

Phase 3: Prepare the New Site

  • Confirm electrical capacity, outlets, compressed air, water and data at the machine locations.
  • Check floor loading and flatness where heavy machines will sit.
  • Confirm door sizes, dock access and any ramps needed.
  • Arrange permits, inspections and sign-offs with your landlord and local authorities as required.
  • Have licensed trades ready for utility connections.

Phase 4: Sequence the Move

Decide which machines move first. Common approaches:

  • Least critical first: Move machines you can live without, and keep your key production machines running until the end.
  • By production line: Move complete lines together so each line is down once.
  • Weekend or shutdown move: Move everything in a planned shutdown window.

Whichever you choose, schedule the machines that need vendor or technician visits around those visits.

RELOCATING YOUR FACILITY?

Get a Quote for Your Factory or Shop Move

Send us your equipment list, floor plans and target dates. We serve Rhode Island, Massachusetts and Connecticut.

Get a Free Quote

Phase 5: Prepare Machines for the Move

  • Have qualified technicians disconnect utilities and photograph and label each connection.
  • Drain fluids and secure moving parts as the manufacturer instructs.
  • Remove and tag tooling, guards and attachments.
  • Strap machines to pallets or skids, and pad or crate delicate parts.
  • Pack small tools, parts and records in labeled containers.

Our packing services and custom crating can protect the equipment, and our storage can hold it if the new site is not ready.

Phase 6: Move Day

  • One decision-maker at each site, with the inventory and floor plan.
  • Routes cleared, floors and doorways protected.
  • Vendors and technicians on site at the agreed times.
  • Each machine placed on the layout, then checked against the inventory.
  • Any problem logged immediately with photos.

Phase 7: Restart and Punch List

  • Level, anchor and connect each machine with qualified technicians.
  • Run test cycles before production resumes.
  • Check inventory, tooling and spares against your list.
  • Log damage, missing items and open issues, and close them out.
  • Update insurance, address records and customer notices.

Insurance, Estimates and Help

Check your own property policy and ask your mover about valuation options. Our guide to released value vs. full value protection explains the difference. Ask for a written estimate and read about binding vs. non-binding estimates.

Correira Brothers’ Moving & Storage handles industrial and shop moves with trained crews, custom crating and phased plans. See our industrial and machinery movers, warehousing and FF&E logistics and shipping and receiving services. For heavy machines, read how to move heavy machinery.

Frequently Asked Questions About Factory and Shop Relocation

How far ahead should I start planning a factory or shop move?

As early as you can. For a full plant, several months is common. For a small shop, 6 to 8 weeks may be enough.

Can we keep producing during the move?

Often, by phasing the move one line or one machine group at a time. Tell your mover your constraints.

What is the biggest cause of delay?

Utilities and vendor schedules at the new site, more often than the move itself. Confirm them early.

Do I need to inventory everything?

Yes. An inventory with weights, dimensions and utilities drives the quote, the sequence and the layout.

Can you store equipment if the new site is delayed?

Yes. We offer short- and long-term storage in Providence and Fall River.